Monday, April 17, 2006

With the roof off we are ready to set trusses for the new roof. The trusses are 54 feet long and will cover the old garage and an 8 foot deck on the long side of the house. Donovan Constructuion sent over a crane and two very capable men to help.
The first truss, a gable end, goes on on the Maple street end of the house.
The box looks naked without a hat. We had shoveled snow out once already.
The first and last six trusses are vaulted for each end of the house. The truss on top of the pile is a vaulted truss. The flat portion goes over the garage which ends up with 11 foot ceilings. Posted by Picasa

Friday, April 07, 2006

Interior demolition begins it's second phase Mid-March '06. The big chimney in the kitchen was boxed in and attached into an unhappily placed wood burner in the basement. It was, of course, installed incorrectly and barely worked. We are glad it's gone. An Anonymous masked worker frosts her hair with blow in insulation. We are greatful to all 16 of our friends that came to help on the first Saturday.
A little light and air helped remove any lingering malodors.
Hey, you big brute. You tore my roof off!
 Posted by Picasa

The rotten garage comes down. After two thirty yard dumpsters of every sort of trash, it was time to remove the roten wood and leaky roof. Here we have removed about a third of the garage. It was fifty feet deep with only one door, so collected everything you wouldn't want in your house.
The first light in years comes into the black hole.
Made it to the end with no major injuries!
 Posted by Picasa